Completed Projects Over a Five-Year Period (2015–2019)
Private
Banco de Oro
Electrical works
- Replacement of 2 x ACB MGM50H1 Rated 5000 Amps to NW50H13D2A including common and extension busbar with mechanical lugs (14 x 250mm2 Lugs per Phase)
- Supply and installation of main circuit breaker and preparation of electrical as-built plans
BDO Dasmariñas Binondo, Mla.
- Installation of 6-5TR FM inverter type ACU electrical works
3rd Floor DCO Makati City
- Installation of new 30KVA UPS unit
6th Floor Dasmariñas Binondo, Manila
- Rehabilitation of main electrical room and metering center
2nd FLoor BDO Dasmariñas Binondo, Manila
Government
City of Lipa, Batangas
PABX and structured cabling
- Supply and installation of 1 lot pabx, voice and data structured cabling
FDAS
- Supply and installation of 1 lot fire alarm & detection system
Private
Dasmariñas Village Association
Electrical designer and consultant
- Electrical design of street lighting
Electrical works
- Electrical installation of Dasmariñas Village Association (DVA) street light
Private
Primehomes Real State Development, Inc.
Electrical Designer & Consultant
- Electrical and auxiliary design of La Rosa Project
ARCONIC
Electrical Designer & Consultant
- Electrical and auxiliary design of Manila North Harbor Port, Inc.
Antonio de Castro and Angelo de Castro
Construction works
- Proposed 2-storey residence expansion renovation with deck
Blk. 559 Lot 6 D. de Castro St., Zaniga Subdivision Mandaluyong City
Addas Group of Companies
Construction works
- 25 units housing construction
Villa Felicia Subdivision, Bayanan, Bacoor Cavite
Addas Group of Companies
Penthouse Adio Centre
Aquinaldo Highway, Talaba
Bacoor Cavite
Construction works
- 20 units housing construction
Villa Felicia Subdivision, Bayanan, Bacoor Cavite
Government
Department Of Health—Main
San Lazaro Compound
Rizal Ave., Sta. Cruz, Manila
Electrical works
- Upgrading of DOH Distribution System and other electrical related projects
Government
Bicol University
Legaspi City
Electrical plumbing and water station
- Supply, delivery and installation of water purifying for BU Spring Water Project of BUCSSP
San Lazaro Hospital
Quiricada St., Sta. Cruz, Manila
PABX and structured cabling
- Replacement and rehabilitation for PABX system of SLH Voice Center
Private
Banco de Oro
Electrical works
- Electrical Backbone of 22-Storey with 4 Basement and Roofdeck
BDO South Tower, H.V. Dela Rosa St., Makati City
- Installation of Electrical Works
Data Center Operations
BDO Ground Floor & 2nd Floor Bldg. 1
Southeast Asian Medical Center
Electrical works
- Installation of Electrical Works
Government
Civil Service Commission Central Office
Constitution Hills, Diliman, Q.C.
Electrical plumbing and water station
- Supply and Installation of 24-Stages Water Purification Equipment, including Electrical and Plumbing Connection
University of Northern Philippines
Vigan City, Ilocos Sur
Electrical works
- Supply of 3 Units 250KVA Distribution Transformer Primary Voltage: 7620/13200 Volts., Wye: Secondary Voltage 120/240Volts, 1 Ø, 60 Hz.
Private
Citibank Savings Inc.
Corporate Realty Services (CRS)
17th Floor Citibank Tower
Electrical works
- Electrical Works
16th Floor Citibank Tower
Banco de Oro
Electrical works
- Electrical Backbone of 4-Storey Building
BDO Remittance, Gil Puyat Ave., Makati City
- Re-Installation of 100 KVA UPS
Makati Data Center
St. Paul Hospital Cavite
Dasmariñas, Cavite
Electrical works
- Installation of electrical Works